Building permit application
Drawings, insertion images and forms: a complete application, filed and followed until the decision.
Starting feefrom €2,500
Typical duration4 to 8 weeks, plus the review

An incomplete application does not get refused: it gets a request for missing documents, and the review period only starts again once everything is in. We put together a complete file the first time, and we answer the planning office for you.
What you receive
- Site plan, floor plans, sections and elevations
- Insertion images showing the project in its surroundings, with photos near and far
- The descriptive notice and the completed forms
- For a new house, the certificate showing the 2020 environmental regulation (RE2020) has been taken into account
- Filing, follow-up and answers to any request for missing documents
Good to know
The review period is two months for a detached house and its outbuildings, three months for other buildings, longer in a protected area. Once granted, the permit is displayed on the plot: neighbours then have two months to appeal. Count on that before booking the builders.
A permit is valid for three years and can be extended twice by one year.